One year left on vSphere 8: plan the migration now, whichever way you go

VMware vSphere 8 and ESXi 8 reach the end of general support on 11 October 2027. After that, Broadcom will ship no more patches, bug fixes, or security updates, and you won’t be able to open a support case. That is twelve months from the day I am writing this, and for most infrastructure teams, twelve months is one budget cycle.

Disclosure first. I work at Leaseweb, on the VMware Cloud team. Day to day, that means supporting customers on the VMware infrastructure we run for them, and designing the architecture of the VMware Cloud Foundation platform we are building as a Pinnacle partner, along with the migration designs that bring customers onto it. I also write about VMware and the European cloud market as an independent analyst, and I did so for years before Leaseweb. In this post, I wear both hats. The analysis is mine and does not speak for Leaseweb, where I describe what Leaseweb offers.

One year left on vSphere 8: plan the migration now, whichever way you go

What actually happens on 11 October 2027

Nothing switches off. Your ESXi hosts keep booting, your VMs keep running, vCenter keeps working, your backups keep running. Nobody at Broadcom is obliged to move you, and you are not obliged to move. What ends is the support contract: no new patches, no security fixes, no support ticket when something breaks. vSphere 8 then enters two years of technical guidance until 11 October 2029, which means workarounds and documentation for known problems on supported configurations, and no new fixes. vSphere 7 crossed the same line on 2 October 2025, so anyone still on 7 is already there.

Broadcom’s own SAP blog from August 2025 also mentions an optional two-year Extended Support period for vSphere 8, available for purchase. If you need it, ask your partner for the terms and price; it is not in the lifecycle dates above.

The risk of staying past the date is a hypervisor under every production workload with no security patches, and a day when you have a Sev 1 and no one to call. A security team can accept that for a defined period, with a dated plan to get off it. The date is fixed, so the plan must exist before it.

Staying on VMware means VCF 9 or VVF 9

There is no standalone vSphere 9. Since VCF 9.0 went GA on 17 June 2025, vSphere 9 ships only inside VMware Cloud Foundation 9 or VMware vSphere Foundation 9; both are subscription, priced per core, with a 16-core minimum per CPU. vSphere Standard and Enterprise Plus stop at 8.0 Update 3. VCF 9.1 and VVF 9.1 went GA on 12 May 2026.

The two bundles are different products, so they have different prices. VVF 9 is vSphere, vCenter, vSAN with a smaller capacity entitlement per core, vSphere Kubernetes Service, and the operations component. VCF 9 adds NSX, HCX, VCF Automation, the SDDC lifecycle layer, a larger vSAN entitlement per core, stretched clusters, and the Private AI services. If your design uses NSX today, or you plan to run stretched clusters, VVF is not an option; if you run on external storage with VLAN networking and no automation layer, VCF is paying for products you will not deploy. Broadcom’s VCF 9.0 feature comparison is the document to read before the quote arrives, because the choice between the two is a design decision that the quote will try to make for you.

The upgrade itself has conditions. According to Broadcom’s VCF 9 FAQ, you must convert perpetual licenses to subscription before any upgrade to 9, and converting or importing an existing vSphere environment into VCF 9 requires vCenter and ESX 8.0 Update 3 or later, with NSX 4.2 or later where NSX is present. Licensing in 9 runs through VCF Operations instead of 25-character keys, so VCF Operations is a required component even in a VVF estate, and an upgrade from VCF 5.x puts the components into evaluation mode until they are re-licensed there. The practical consequence: if you are on 8.0 Update 2 or earlier today, the path to 9 is two upgrades, and the first one has to happen while 8 is still in general support.

Hardware is the other gate. Broadcom’s VCF 9.0 server certification post says most servers certified for vSphere 8.x carry forward, and that a server drops off the 9.0 list when a core component is fully end of service life, with Intel Haswell and Broadwell as the examples. Skylake and Cascade Lake sit in a “VCF Supported, Confirm with Vendor” category, where Broadcom supports the software and the OEM must confirm the hardware; the same post says Skylake may need an RPQ exception. Check every host model in the Broadcom Compatibility Guide before you size the license, because a cluster that cannot run ESX 9 changes the whole math: you are now buying servers and licenses in the same year, or running VVF 9 on new hosts next to vSphere 8 on the old ones.

The support model changed with VCF 9. Broadcom moved from the old 5+2 model to a 6+1 model: six years of support from the major release, plus the option to buy one more year of Extended Support, with a new major release every three years and a minor release roughly every nine months. For VCF 9, that puts the major line into 2031. Each minor release (9.0, 9.1) has its own shorter window inside that, so check the version you plan to land on in Broadcom’s lifecycle portal, not just the major line.

Two licensing facts matter for the math. First, Broadcom announced a 72-core minimum purchase per product for new and renewal orders from 10 April 2025, covering VCF, VVF, vSphere Enterprise Plus, and vSphere Standard. German trade press reported within days that Broadcom withdrew it and kept the 16-core-per-CPU minimum, and Broadcom said it had never announced a price change. Resellers have kept quoting 72 cores as the smallest line on some deals since. Get the minimum in writing on your own quote before you believe either version. Second, a late renewal carries a 20 percent surcharge on the first year of the renewed subscription. Your renewal date, not October 2027, is the real deadline.

Why twelve months is tight

Twelve months is enough to decide and start executing, but too short to finish a large migration. Gartner research VP Julia Palmer told The Register in September 2025 that a full migration off VMware takes three or more years, and that re-platforming selected applications can take up to a year on its own. That matches what I have seen.

As a freelancer, I worked on migrations from VMware to other hypervisors for 500 VMs and 3,000 VMs, and planned one for 7,000 VMs. Two things I learned apply to every size.

First, most environments aren’t lift-and-shift, and it’s never a next-next-finish. A migration between hypervisors needs a plan built from an inventory of each VM, and the inventory has to answer technical questions that a VM count hides.

One year left on vSphere 8: plan the migration now, whichever way you go

Start with the guest. Which OS versions are in the estate, and does the target hypervisor support them with its own drivers? A Windows VM carries vmxnet3 and PVSCSI; on the target, it needs the integration services or virtio drivers installed before the first boot, or it comes up without network and without its data disk. A Linux VM needs the target’s storage and network modules in the initramfs, or it stops at the boot prompt. VMware Tools has to come out, and the order matters: remove it after the final sync and before first boot on the target, because removing it early on the source drops the IP configuration, MAC address, and routing table, and you spend the cutover window typing them back in. That order is the reason I wrote cleanup scripts instead of doing it by hand.

Then the virtual hardware. Firmware mode (BIOS or UEFI) must match on the target, and Secure Boot and vTPM are a separate problem: a Windows VM with BitLocker tied to a vTPM needs the recovery key before it boots on a new TPM, and that key has to be in hand before the migration, not after. Disk format changes (VMDK to VHDX or qcow2) are mechanical, but thin and thick provisioning, disk alignment, and SCSI controller order are not; the wrong controller order on a multi-disk database server boots the VM from the wrong disk. MAC preservation keeps the application licenses that are tied to it; if the target cannot keep the MAC, find every license tied to one before you move. Linux VMs are the hardest of all because the boot path and device naming differ from distro to distro and sometimes from version to version. That is why I wrote migration scripts for the pre- and post-migration steps and published them in my Scripts-Provirtualzone repository on GitHub: a Windows toolkit covering network backup, VMware Tools removal, network restore, disk validation, and device cleanup, plus a GPO edition for unattended deployment, and a Linux toolchain for RHEL, CentOS, Oracle Linux, and Debian from EL6 to EL9. The Linux side is on hold in the repository, so treat it as a starting point and test it per distro before you rely on it.

Then everything around the VM. Backup jobs point at vCenter and a VM ID; the migrated VM is a new object, so the backup chain starts again with a full, and the first full of 3,000 VMs is a storage and bandwidth event you plan for. Replication to the DR site stops at cutover and must be rebuilt on the new platform before the VM is protected again. Monitoring that polls ESXi or reads vCenter alarms goes blind for every migrated VM until the target’s monitoring is in. Affinity and anti-affinity rules do not travel; two domain controllers that DRS kept apart can land on the same target host. DHCP reservations, firewall rules keyed to MACs, and load balancer pools keyed to VM names all need checking.

Then the data movement itself, which is where twelve months disappears. A cold migration of 3,000 VMs at 100 GB each is 300 TB; at an effective 2 Gbit per second, that is roughly 14 days of continuous transfer, and no business gives you 14 days of downtime. The only way to do it is a warm sync, where the data copies while the VM runs and only the changed blocks move at cutover, in waves grouped by application dependency, in maintenance windows the application owners agree to. Changed Block Tracking keeps the delta small; cutover windows, dependency mapping, and application owners’ calendars set the schedule, and those are measured in months.

Second, post-migration is a project of its own and has to be planned before the first VM moves. The VM boots on the new hypervisor and then the work starts: driver cleanup, orphaned tools, backup re-protection, monitoring, DR replication rebuilt on the new platform, the tickets from application owners who find the one thing nobody tested. I wrote the cleanup part up, with the PowerShell scripts, in How to Safely Clean Up Your Windows VMs After a VMware Migration using Veeam on the Veeam Community Resource Hub, and went through the whole migration flow with Julia Morgado in Veeam 100 Show #14, migrating VMs from VMware to Hyper-V with Veeam. I gave a second session on migrating from VMware to Proxmox with Veeam; that one was not recorded, so the Hyper-V show is the one to watch, and the steps are the same with a different target.

Comparing vSphere with Proxmox is the wrong question

Every week someone posts a side-by-side of vSphere and Proxmox, or Hyper-V, and concludes that one wins. They are not the same product, and they will not be in the near future. Proxmox has existed for years and has improved faster in the last two than in the ten before, and it is still a long way from vSphere on the things that matter under load: DRS placement and its rules, HA behavior under host isolation and partition, vMotion and storage vMotion at scale, Fault Tolerance, the vSAN and NSX stacks, VM hardware compatibility levels, and the application vendor support matrices that certify SAP, Oracle, and Microsoft workloads on each platform. Some of those have equivalents on other hypervisors, some have partial equivalents, some have nothing. If you think the gap is just NSX or vSAN, you have not run both in production.

That is a different question from whether Proxmox fits a given VMware customer. For many, it does. A company with three, four, or five hosts, running VMs on external storage, using no NSX, no vSAN, and half of the features it pays for, has no technical reason to pay the new prices, and with the price increases it has every financial reason to move. Those customers are leaving, and they should.

The companies that stay are a different group, and they are not staying because leaving is hard. The large majority stay because of the product: in twenty years of running vSphere and other hypervisors, and migrating between them, I have not seen another platform match it for reliability and feature depth on critical workloads, and the vendor support matrices for the applications on top of it say the same. That is my judgment, and the disclosure at the top of this post applies. The companies in that group that do leave usually leave over the commercial relationship with Broadcom, not over the product.

The open source argument lands in the wrong place as well. Enterprises run critical workloads on open source code every day, on Linux, on KVM, on PostgreSQL, and not one of them runs the community build. They buy the commercial product built on it, from a company that tests it, certifies the hardware and software around it, ships the patches, and answers the support call. By the time a multibillion-dollar company stands behind the product, what the customer runs is that company’s product, and the open-source license underneath is not what they are paying for. Proxmox works the same way: the hypervisor is open source, and the subscription from Proxmox Server Solutions is the product. So the comparison that matters is supported Proxmox against supported vSphere, on what each vendor certifies and will stand behind for your critical workloads: the hypervisor, the backup and monitoring vendors, the hardware vendors, and the application vendors that will take your support call when the workload runs there. Make that comparison before the license savings decide anything.

The most common result I have seen is neither all-in nor all-out. As a freelancer, I led a migration from VMware to Hyper-V where the company moved around 30 percent of its workloads, roughly 700 VMs, all non-critical, and kept the critical ones on VMware. The license savings on the 30 percent paid for the project, and the workloads that needed vSphere stayed on it. For a mid-size company with a mixed estate, that split is usually the answer, and it means the feature list per workload, not per company, decides where each VM goes. Write down what each critical workload depends on today, check it against the target, and only then compare prices. If the target cannot run your ERP under its vendor’s support terms, the license saving pays for the outage.

Small environments: do the math

If you run two, three, or four hosts, ask: is VCF 9 worth paying for? Is VVF 9 worth it, with a smaller price increase? Or do you move to a cheaper hypervisor and pay the migration cost from the section above instead of the license cost?

The deciding factor is your licensable core count against the minimums on your quote. Four hosts with two 16-core CPUs is 128 cores, and the 72-core question never comes up. Two hosts with one 8-core CPU each is 16 physical cores, licensed at 32 under the 16-core per CPU floor, and if a 72-core line minimum appears on the quote, you pay for 72. At that size, if your workloads don’t depend on vSphere-only features, I wouldn’t pay for VCF 9. VVF 9 is the middle option if the quote stays close to your physical cores. If it does not, the migration cost is the cheaper number, and you plan the migration with the checklist above. A small environment has fewer VMs, and the same number of things that can go wrong per VM.

Where to go if you decide to stay on VMware

For environments bigger than a few hosts, there are three routes. Upgrade to VCF 9 in your own datacenter and own the licensing, the platform build, and the Broadcom relationship. Move to a VMware Cloud Service Provider that runs VCF for you. Or leave VMware, with the migration plan above.

The second route is the one I want to say something about, because I work in it. The Broadcom partner changes left customers without the partner that used to sell them licenses and open their tickets. If that is you, the move I would make is to a VCSP Pinnacle partner, and my pick is Leaseweb, where I work. On 14 July 2026, Leaseweb announced it is a VMware Cloud Service Provider Pinnacle tier partner in the Broadcom Advantage Partner Program for the European Economic Area, Singapore, and the United States. Pinnacle is the program’s highest tier, and Leaseweb says it includes a direct working relationship with Broadcom for support escalation and roadmap. The same release puts Leaseweb at 28 data centers on its global network, calls it the only Dutch cloud provider taking part directly in the EU’s IPCEI-CIS program, and says VMware Cloud Foundation will be delivered as managed private cloud and sovereign cloud services from that footprint. Two days later, Leaseweb and ITQ announced a partnership to deliver VCF services across Europe, with ITQ’s advisory and migration work running on Leaseweb’s platform.

The implementation and the customer migrations are done by our VCF team, including some migrations that were far from simple and went through cleanly, with more in the pipeline, and day-to-day operations are handled by our support team. I work with both every week, and I know the effort we put into every migration and support for our new VCF infrastructure. If you decide to move to Leaseweb, they’ll move your workloads and answer the phone afterward. My opinion on their quality is as a colleague, not a company claim.

Moving to a VCSP is still a migration. The guest OS checks, the application dependencies, the backup and monitoring rebuild, and the post-migration work all apply. Because the target is vSphere, the feature-gap check is the one part of the plan that gets shorter.

The next twelve months

The next months will show where the market goes. VMware Explore on Tour reaches Frankfurt on 13 and 14 October and London on 18 and 19 November, and I will be watching for two things. Does Broadcom announce anything for smaller customers, the two-to-four-host estates that the core minimums and the VVF pricing hit hardest? And does it try to win back the customers already testing Proxmox or another hypervisor with pricing, a migration offer, or a partner program change, or does it let them go and keep its focus on the large accounts it has already converted? By the end of 2027, we will have a real view of how Broadcom handled this end of support and how companies handled it, because by then the renewals will have been signed or not, and the migrations started or not.

Whichever route you take, the plan for the next year looks the same at the start. Before the end of 2026, build the inventory: every cluster, host, VM, guest OS, application dependency, and vendor certification, and find your renewal date, because that date decides when you must have chosen. In the first quarter of 2027, classify workloads as move early, move later, or stay for now, and run the feature-gap check against your target. By the second quarter, run a pilot with a representative sample and measure what breaks, how long cutover takes, and what the post-migration list really contains. From the third quarter, move the first production wave, update backup, monitoring, and runbooks as you go, and size whatever stays on vSphere 8 for the remaining support or Extended Support you will need.

A large estate will still be mid-migration in October 2027. The difference starting now is that by then the decision rests on your own test results, and the hosts still on vSphere 8 are the ones you chose to leave there, with a date on them.

Share this article if you think it is worth sharing. If you have any questions or comments, leave them here or contact me on Twitter (yes, for me it’s not X, but still Twitter) or LinkedIn, since I am getting off Twitter.